SpaceX won’t remove all of xAI’s unpermitted turbines for another year

SpaceX is building a new power plant for xAI's Colossus data centers, but it won't remove existing, unpermitted turbines for many more months.

SpaceX won’t remove all of xAI’s unpermitted turbines for another year

TL;DR

  • SpaceX will remove unpermitted turbines powering xAI data centers near Memphis.
  • The transition is part of building a permanent 1.2 gigawatt natural gas power plant.
  • Complete removal of the turbines is scheduled for July 2027.
  • SpaceX is currently operating 69 gas turbines for the Colossus data centers.
  • The NAACP and Southern Environmental Law Center have sued xAI over the use of unpermitted turbines.
  • SpaceX claims turbines are exempt from permits because they remain on trailers.
  • Federal regulations state these turbines require permits due to their size and usage.
  • The Department of Justice sided with SpaceX, citing national, economic, and energy security.
  • The new power plant will consist of 41 gas turbines.
  • Elon Musk previously acquired APR Energy, which specializes in temporary natural gas power.
  • Turbines from APR Energy are likely intended for an unannounced project, not the new permanent plant.