Oct 20, 2026

Microsoft Walks Away as Essex AI Hub Waits for Power

Microsoft has withdrawn from Nscale’s proposed Essex AI data centre after learning power may not arrive until the 2030s. Nscale says the project will continue and its broader work with Microsoft remains intact.

Microsoft has pulled out of a deal to support Nscale’s planned AI data centre in Essex, a setback for what had been billed as the UK’s largest such project.

The decision followed a warning from local electricity-grid officials that the site would not receive power until the 2030s. For a facility intended to serve the power-hungry AI boom, that timetable turned a flagship plan into a long wait.

The withdrawal does not, however, mean the site has been abandoned. Construction is still expected to proceed without Microsoft’s backing, according to the account of the deal’s collapse.

Nscale’s position is notably more defiant than Microsoft’s retreat. The British company says its partnership with Microsoft on other projects “remains strong,” framing the Essex reversal as a problem for one development rather than a rupture in the wider commercial relationship.

The episode leaves an awkward contrast. Microsoft has treated the delayed grid connection as reason enough to walk away; Nscale is pressing on, betting the project can outlast the power bottleneck. The immediate loser is the timetable for a major AI hub — and the broader warning is clear: data-centre ambitions can be announced quickly, but electricity infrastructure moves on a far slower clock.